Construction progress monitoring with drones: tracking and reporting

How construction progress is monitored and reported with drone surveys: what a flight measures that a site walk cannot, how often to fly, and what goes in the monthly progress report.

Published · 9 min read · By Malya, the makers of Clarity

Progress monitoring answers one question every week or month: is the job where the programme says it should be, and if not, by how much? The answer is made of quantities, dates and a record of the site, and most of the argument on a construction project is about whose version of those is right. This guide is about producing a version that holds, using drone surveys for the part they are best at: measuring the whole site, the same way, every time.

What progress monitoring is made of

  • Quantities. Cubic yards excavated, placed and compacted; tons of stone in the yard; area paved; the level a pad or a dam has reached. Quantities are what valuations and claims are paid on.
  • The plan. The programme or schedule, and the planned quantities for each period. Progress is only meaningful against it.
  • The record. What the site looked like on each date. Rarely needed, and invaluable the day a delay or a defect is disputed.
  • The actions. What is behind, why, and who is fixing it by when.

The ways progress is tracked, and what each can measure

MethodMeasuresMisses
Site walk with photosAnything a person can see and judge; quality; conversationsQuantities; the whole site at one moment; a consistent record
Fixed time-lapse cameraA continuous visual record from one viewpointAnything out of its view; quantities
Survey with a roverPrecise points and levelsThe surface between the points; it is slow over a large site
Schedule updateActivities started, finished and percent completeWhether the reported percent matches what is in the ground
Drone surveyThe whole site's surface and appearance on one date; volumes between datesInside structures, under cover, behind formwork
The common methods, side by side. Most projects use more than one.

A drone flight is the one method that measures quantity across the whole site at a single moment, which is why it has become the backbone of progress reporting on earthworks, civil, mining and large building sites. It works best as the measured layer under the schedule and the site walk, not instead of them.

Monitoring progress with drone surveys

  1. Fly on a fixed cycle, the same day of each week or month, with the same flight plan: height, overlap and roughly the same time of day. (Flight settings.)
  2. Position every flight the same way: ground control left in place, or RTK or PPK with a few checkpoints. Two flights that disagree about where the ground is produce progress that never happened. (What each method gives you.)
  3. Keep every flight on one timeline for the site, so this month's map sits beside last month's and the first.
  4. Measure the change, not just the state: difference this flight against the last one for volume moved, and against the design for what is left to do. (Comparing two flights.)
  5. Pin the walk's photos and issues to the map where they were taken, with a name and a date on each action.
  6. Write the report from those, and keep it with the flights it was made from.

What a drone flight tells you that a walk cannot

  • Earth moved this period, in cubic yards, cut and fill separately, over the whole site or inside the boundary of each work area.
  • What is left to design, as cut and fill remaining against the engineer's surface. (How cut and fill is calculated.)
  • Stock on hand, pile by pile, in tons. (Measuring stockpiles.)
  • Levels reached: a pad at subgrade, a dam at its next lift, a cross-section along a haul road against last month's.
  • Where things are: laydown areas, haul routes, the extent of each crew's work, drawn on a map that is true to scale.

The monthly progress report

A good progress report is short and built from things that can be checked. A structure that works for most civil and earthwork jobs:

SectionWhat it saysWhere it comes from
SummaryWhere the job stands against the programme, in three or four sentencesThe project manager, from everything below
QuantitiesThis period and to date against plan: excavation, fill, stone, pavingVolumes between this flight and the last, and against design
The site nowA current orthomosaic, and the difference map for the periodThe flight
PhotosAnything that matters, each pinned to where it was takenThe site walk
Issues and actionsWhat is behind, why, who owns the fix, by whenThe action list
Look-aheadWhat the next period should achieveThe schedule
A construction progress report, section by section, and where each part comes from.

Where progress numbers go wrong

  • Two flights at different heights. Without the same control each time, a whole site can read as tens of thousands of cubic yards of cut that nobody dug. Check the offset on ground that did not change before reading any number.
  • Comparing the wrong surfaces. A truck parked on a pad last month and gone this month reads as cut. Fly when the site is still, or compare the terrain models. (DSM, DTM and which to compare.)
  • Survey noise counted as work. Two good flights disagree by a few centimetres everywhere; over a large site that is real-looking volume. A deadband of about the noise level keeps it out.
  • Percent complete by opinion. A schedule updated by judgement drifts from what is in the ground. Measured quantities are the check on it.

How often to fly

Monthly suits most valuations and most clients. Weekly suits fast bulk earthworks, a programme in trouble, or a client who wants to watch. More often than weekly is rarely worth processing unless a specific operation, such as a large pour or a blast, needs a before and after. Whatever the cycle, keep it: a series of flights is worth far more than the same number of flights taken when someone remembered.

Doing it in Clarity

Clarity keeps every flight of a site on one timeline, plays them back as a film, swipes and differences any two dates, flags two flights that sit at different heights and lets you level them on unchanged ground, measures cut and fill against the design or the last flight with a deadband, and pins field quality observations to the map with a name, a due date and a review workflow. The measurements print as a report per flight, the observations export to Excel, and a share link lets the client open the site with no account. (Progress monitoring in Clarity.)

Questions people ask

What is construction progress monitoring?

Comparing what has been built with what was planned, at regular intervals, so that slippage is seen while it can still be recovered. It covers quantities (how much earth has moved, how much has been placed or paved), milestones and the schedule, and the record of the site at each date that a later dispute will ask for.

How are drones used for construction progress monitoring?

The site is flown on a regular cycle, usually weekly or monthly, and each flight is processed into a map and a terrain model. Comparing two flights shows where ground was cut or filled and by how much, how far a structure or a pad has risen, and what changed, as measured quantities rather than impressions. The maps also become a dated visual record of the whole site.

How often should a construction site be flown?

Monthly is enough for valuations and the monthly report on most civil and earthwork jobs. Weekly suits fast earthworks, short programmes and sites where the client watches closely. Fly on the same day of the cycle each time, with the same flight plan and positioning, so that the flights compare cleanly.

What goes in a construction progress report?

A short summary of where the job stands against the programme; quantities completed this period and to date against the plan; the site as it looks now, with photos of anything that matters; issues, risks and who owns each; and a look-ahead to the next period. Drone surveys supply the quantities and the site picture; the schedule supplies the plan they are compared with.

Can drone surveys replace site walks?

No, and they are not meant to. A flight measures the whole site's surface in an hour and catches what a walk would miss, but it cannot see inside a structure, under a roof or behind formwork, and it cannot talk to the foreman. The strongest routine pairs a regular flight with a site walk, with the walk's photos pinned to the map where they were taken.